beam time4/3/066/20/06 0

                    
measurements4/3/066/18/06 0

                    
setup4/3/064/8/06 0

                    
det setup4/3/064/8/06 0

                    
beam tuning4/6/064/8/06 0

                    
production4/8/066/8/06 0

                    
systematics6/9/066/18/06 0

                    
nat H26/12/066/18/06 0

                    
Ar6/9/066/14/06 0

                    
AK36/13/066/14/06 0

                    
APD scint6/13/066/14/06 0

                    
preparations3/20/063/31/06 0

                    
shipping UIUC hardware3/22/063/29/06 0BK

                    
shipping new computers3/24/063/31/06 0PK
include disks, logic probe
new AK3 target3/29/063/31/06 0PW
discuss with Bernhard
APD scint3/20/063/29/06 0SK, PK

                    
detectors3/22/064/6/06 0

                    
TPC3/22/063/26/06 0

                    
HV ramping3/20/063/27/06 0CP, MH

                    
electronics noise3/27/063/30/06 0GP

                    
mDet4/3/064/4/06 0BK

                    
eSC3/28/064/5/06 0

                    
replace poor PMs3/28/063/31/06 0BK, PW

                    
check poor scintillators3/28/063/31/06 0BK

                    
optimize thresholds4/3/064/5/06 0PK

                    
install new HV3/28/063/31/06 0BK, PW

                    
ePC3/27/064/6/06 0

                    
start HV ramping3/27/064/1/06 0PW

                    
fix electronics, wires3/31/064/3/06 0PK

                    
optimal threshold, eff, HV4/3/064/8/06 0BK, SC

                    
nDet3/28/064/1/06 0

                    
mount + HV on3/28/064/1/06 0BK, PW

                    
Gas system3/20/064/4/06 0

                    
Isotope sep.3/20/063/31/06 0CHUPS

                    
decision on Pd filter4/3/064/4/06 0PK

                    
H2O calibrator3/20/063/22/06 0

                    
CHUPS+TPC test3/22/063/29/06 0MH, MV

                    
daq+electronics3/20/064/30/06 0

                    
remove LRS ADC+logic3/29/063/31/06 0BK

                    
make WFD perfect4/4/064/9/06 0TG

                    
WFD compression3/30/064/4/06 0FG

                    
neutron FADC3/31/064/6/06 0FG

                    
TPC FADC4/24/064/30/06 0FG

                    
prepare trigger cabling3/20/063/26/06 0PK

                    
TPC trigger3/28/064/10/06 0PK

                    
new CPUs3/31/064/7/06 0

                    
analysis3/17/064/15/06 0

                    
online3/17/064/15/06 0

                    
define online spectra3/17/064/1/06 0BK, PW

                    
implements online spectra4/3/064/9/06 0FG

                    
develop pages and scripts4/5/064/15/06 0BK, SK, PW

                    
offline3/17/063/18/06 0

                    
define Steve's tasks3/17/063/18/06 0SC

                    
Presence at PSI3/19/066/20/06 0

                    
Tim3/19/063/20/06 0

                    
Fred3/30/066/19/06 0

                    
Peter3/31/065/1/06 0

                    
Brendan3/28/066/20/06 0

                    
Bernhard4/4/064/12/06 0

                    
Sara4/5/066/20/06 0

                    
Malte3/19/063/20/06 0

                    
Claude3/19/063/20/06 0

                    
Rene3/19/063/20/06 0

                    
Peter W3/27/066/20/06 0

                    
Francoise5/18/065/21/06 0

                    
Marat3/19/063/20/06 0

                    
Sacha3/19/063/20/06 0

                    
PeterII3/19/063/20/06 0

                    
G Petrov3/19/063/20/06 0

                    
Evgenny3/19/063/20/06 0

                    
Oleg3/19/063/20/06 0

                    
Gennady3/19/063/20/06 0

                    