Re: swot



Dear Peter and all,

Excuse us please for a late answer - we spend all the time around the
new cryogenic system.

Our proposals about the CHUPS SWOT

Strength

- new pipelines design (more stable and consistent);
- new pressure stabilisation algorithm (includes hardware and software
improvements) - better pressure stability;
- new stable electronics;
- humidity on-line measurements;
- remote L-nitrogen filling.

Weakness

- ice on the top of the compressor unit;
- humidity sensor overheating;

Opportunities

The system is quite ready for the next run.

Tasks

1. Install additional fans to blow the compressor unit and the
humidity sensor to solve mentioned problems;
2. The main task - design and manufacturing of the new cryogenic
system for deuterium elimination.

Best regards,

Marat, Sasha, Peter the 2nd.

2006/1/24, Peter Kammel <kammel@npl.uiuc.edu>:
> Dear colleagues,
>
> This afternoon I updated the SWOT draft. Please don't hesitate to
> enter your comments and recommendations to ALL parts of
> the document. We can streamline the draft later.
>
> In case you are not used to the cvs procedure, I have
> attached a pdf version of the draft. You are welcome
> to mail comments to me and I will include them.
>
> Best regards
>
> Peter
>
>
>