RE: MuLan / MuCap exchange



Folks,
	I was under the impression we would begin the exchange on
Monday, the 24th (at the earliest).  If things are going well, one could
consider waiting an extra 1 or 2 days.  

	We need to get an estimate of the work plan to make the
exchange.  If MuCap will keep the beamline as is (they will), then we
are talking about
1) Removing MuLan (0.5 days)
2) Putting in mag shielding ( ??? days )
3) Installing MuCap expt. (1 day ?)
4) Installing MuCap "House" (0.5 day ?)

	Let's all discuss this very soon to make estimates.  Perhaps
Peter Winter can find out about the work plan for the mag shielding work
(that is, the time involved).  PK can give an update on the readiness of
the Cap to go in.  

	Also, PW, can you find out when the Cobra magnet is scheduled to
turn on?  If not before MuLan leaves, then perhaps we can organize a
test with them and have them put it on while we run for an hour.  That
way, we can take a calibration with the field on and find out how many
of our tubes are affected.

	Regards,
	Dave

-----Original Message-----
From: Peter Kammel [mailto:kammel@npl.uiuc.edu] 
Sent: Tuesday, October 04, 2005 6:46 AM
To: David Hertzog
Cc: Peter Winter; 'Francoise Mulhauser'
Subject: Re: MuLan / MuCap exchange

Dear Dave,

I thought the official change between experiments in piE3
is on Monday  :)

We certainly can talk about the 2 additional days, if necessary.
But they will also need some time to install the magnetic
shielding which will be taken from Mucap allocation.

Best regards

Peter



On Tue, 4 Oct 2005, Peter Winter wrote:

> Hello,
> 
> I have been to the Montage-Meeting this morning. At the moment the 
> schedule foresees the exchange of the two experiments from
> 
> Wed., 10/19 til Fri., 10/21.
> 
> I asked about the availability of the crane in the following week 
> (10/24-28) and there are no problems in case that we want to shift the

> exchange to that week. If so, we only have to tell them because the 
> schedule is different at the moment.
> 
> Furthermore, I was asked:
> - if we already know about the changes in the beamline (kicker,
seperator?).
> - what to do with the MuLan ball and the barrack? I was told that for 
> the period of the shutdown the place downstairs should be free. Maybe 
> the barrack by Mr. Simons might be moved away and ours remain there
but 
> that's not sure, yet.
> 
> Best greetings
> Peter
>